Town of Putnam Valley Projects Overseen by J. Robert Folchetti & Associates (JRFA)  February 17, 2026

FEMA

  • Wiccopee Road Culvert – Construction complete 
  • Bell Hollow Road Culvert – Construction complete 
  • Town Hall Parking Lot Retaining Wall – Construction complete
  • Town Park Beaches at Lake Peekskill and Oscawana Lake – Construction Complete
  • Brook Falls Road Culvert – Construction ongoing, to run through June 2026 – Temporary bridge in use, footings for arched concrete culvert to be delivered week of March 2, 2026. Arched concrete culvert sections to be delivered week of March 9, 2026. New arched structure to be installed by April 30 with paving, site restoration and guiderail installation thereafter.
  • New Hill Road Culvert – 85% Design Complete working on NYSDEC and ACOE approvals. Temporary bridge installation during construction included in the design documents.
  • Cimarron Road Culvert – Bids received on January 12, 2026. Bid review and recommendation complete, bid award estimated on February 18, 2026. Construction to start approximately 45 days later.
  • Horton Hollow Road Bridge – 24% Design Complete working on engineering report, property acquisition documents, subsurface soil borings, tree removal and NYSDEC and ACOE approvals. 
  • Oregon Corners Substation Demolition – Bids received in December 2025. Bid award is estimated on February 18, 2026. Demolition takes place within 45 days of contract signing. 

 

As we transition out of winter, the Putnam Valley Highway Department continues to stay active across town, addressing seasonal damage and preparing for upcoming projects. With warmer weather on the horizon, crews have already begun a wide range of improvements to ensure safer and smoother travel for residents.

Over the past several weeks, the department has reinforced approximately 500 feet of ditch line along Indian Hill Road using pad rock gravel to help prevent vehicles from veering off the roadway. On Wood Street, an additional 200 feet of 12-inch pipe has been installed alongside similar gravel reinforcement to improve drainage and road stability.

Crews have also been actively repairing dirt roads throughout town and restoring lawns and intersections impacted during winter snow removal operations. Cold patching efforts are underway, and the department is preparing for the upcoming paving season. A meeting with the Town’s blacktop contractor is scheduled for next week, after which the paving list will be finalized. Pending the approval of the New York State budget and potential funding increases, paving is expected to begin in late June through early July.

Additional roadside work includes the removal and reduction of ledge rock along various roadways. This effort will not only improve plowing conditions in the winter months but also enhance driver safety and visibility in key areas.

Several infrastructure projects are also moving forward. The Brookfalls Road culvert project remains in the bidding phase, while work on the Cimarron Road culvert is expected to begin soon. The Horton Hollow and New Hill culvert projects are currently in the design stage. Updates on timelines and progress will be shared with the community as they become available.

The department is also preparing to resume basin cleaning and repair operations once temperatures stabilize and conditions allow for safe equipment use.

Following discussions with Putnam County DPW, proposed changes to Adams Corners were evaluated but ultimately determined to be both unsafe and cost-prohibitive.

Residents are reminded that the Highway Department is available 24/7 to address concerns. For the most efficient response, residents are encouraged to contact the department directly rather than posting issues on social media.

To stay informed on ongoing work and updates, residents can follow the Town of Putnam Valley Highway Department on Facebook.

For assistance or to report an issue, please contact the Highway Department at 845-526-3333, or reach out via email at skeeler@putnamvalley.gov.

The Town of Putnam Valley continues to advance multiple infrastructure and recovery projects overseen by J. Robert Folchetti & Associates (JRFA). These efforts focus on strengthening roads, culverts, bridges, and public facilities throughout the community while improving safety and long term resiliency.

FEMA Funded Projects

Several FEMA related improvements have already been completed:

  • Wiccopee Road Culvert – Construction complete

  • Bell Hollow Road Culvert – Construction complete

  • Town Hall Parking Lot Retaining Wall – Construction complete

  • Town Park beaches at Lake Peekskill and Oscawana Lake – Construction complete

Additional projects are currently in progress or moving through design and bidding phases:

Brook Falls Road Culvert
Construction is ongoing and expected to continue through June 2026. A temporary bridge is in use. Footings were delayed due to freezing conditions. Arched concrete culvert sections are scheduled for delivery the week of March 9, 2026. The new arched structure is anticipated to be installed by April 30, followed by paving, site restoration, and guiderail installation.

New Hill Road Culvert
Design is approximately 80 percent complete. The team is working through NYSDEC and ACOE approvals. Plans include a temporary bridge installation during construction.

Cimarron Road Culvert
Bids were received on January 12, 2026. Bid review and recommendation are underway, with an award estimated on February 18, 2026. Construction is expected to begin approximately 45 days after the award.

Horton Hollow Road Bridge
Design is approximately 20 percent complete. Current work includes the engineering report, property acquisition documentation, subsurface soil borings, tree removal, and NYSDEC and ACOE approvals.

The goal is to have all FEMA projects completed by December 31, 2026.

Additional Town Project

Oregon Corners Substation Demolition
Bids were received in December 2025. The bid award is estimated for February 18, 2026, with demolition scheduled to occur within 45 days of contract signing.

These projects represent continued investment in the Town’s infrastructure and long term reliability of critical public assets. Additional updates will be shared as work progresses.

The Roaring Brook Lake Dam Improvement Project was recently completed by Doyle Contracting Inc. A final walkthrough of the project site was completed by Town of Putnam Valley Supervisor Alison Jolicoeur, Town Engineer Todd W. Atkinson, P.E., WSP engineering staff and Roaring Brook Lake Manager Sam Lee on January 13, 2026. The dam improvement project was designed and constructed to bring the Roaring Brook Lake Dam into compliance with NYSDEC Dam Guidelines.

Water levels are maintained by the Dam Master throughout the winter season.

The Town of Putnam Valley Highway Department extends its thanks to the men and women of the department for their continued hard work and dedication over the past four years, especially during the recent stretch of cold and snowy weather. Their around the clock efforts help keep our roads safe and passable for residents all winter long.

As we move through the season, residents are reminded of several important winter safety guidelines:

  • No parking on town streets during the winter months or during snow emergencies, as parked vehicles make plowing difficult and prevent proper clearing of the roadway.
  • If your vehicle becomes stuck during a storm, please do not abandon it. Contact the Highway Department for assistance.
  • It is illegal to shovel or plow snow into the roadway, whether clearing your own driveway or using a snow removal service.
  • Clearing a few extra feet at the end of your driveway can help reduce the amount of snow pushed back in by passing plows.

Brining the Roads

Residents have asked about pre-storm brining of roadways. The Town’s current brine system is approximately 26 years old, outdated, and out of service, with repair costs estimated at $15,000. Replacing the system would cost roughly $225,000, and modern systems require significant water infrastructure, potentially adding another $750,000 for wells and facilities.

In addition to the high cost, the effectiveness of brining has diminished with today’s response methods. Highway crews now salt roads quickly once snow begins, often within the first hour, reducing the need for advance brining. Brine treatments also cost approximately $7,500 per application and can lose effectiveness if applied too far in advance of a storm.

There are also environmental and infrastructure concerns. Salt brine can accelerate vehicle corrosion, damage catch basins and concrete structures, and potentially affect nearby vegetation. In recent years, the Town has seen fewer basin repairs after reducing brining practices. Many neighboring highway departments have reached similar conclusions and have scaled back or discontinued brining.

Stay Connected

The Highway Department is available 24/7 for service requests and concerns. Residents are encouraged to contact the department directly rather than posting issues on social media, as direct calls allow for faster response.

Highway Office: 845-526-3333
Cell: 845-745-0795
Email: skeeler@putnamvalley.gov

Thank you for your cooperation and for helping keep Putnam Valley safe this winter.