Bridges & Colverts Projects around Putnam Valley Updates

Town of Putnam Valley Projects Overseen by J. Robert Folchetti & Associates (JRFA)

 May 6, 2026

FEMA Projects

  • Wiccopee Road Culvert – Construction complete 
  • Bell Hollow Road Culvert – Construction complete 
  • Town Hall Parking Lot Retaining Wall – Construction complete
  • Town Park Beaches at Lake Peekskill and Oscawana Lake – Construction Complete
  • Brook Falls Road Culvert – Construction ongoing, to run through June 2026 – Temporary bridge in use. Culvert footings, arched concrete culvert sections, wingwalls and headwalls are installed. Project work to be completed includes paving, site restoration and guiderail installation.
  • New Hill Road Culvert – 95% Design Complete working on NYSDEC and ACOE approvals, received New York State Office of General Services “no permit required” document. Temporary bridge installation during construction included in the design documents.

Capital Projects

  • Horton Hollow Road Bridge – 30% Design Complete working on engineering report, property acquisition documents, subsurface soil borings, tree removal and NYSDEC and ACOE approvals. 
  • Cimarron Road Culvert – Bids received on January 12, 2026. Bid review and recommendation complete and  bid award complete. Contract to be signed by May 8, 2026. Construction to begin week of May 11, 2026. Bridge will be closed, detour to be installed by contractor.
  • Oregon Corners Substation Demolition – Demolition Complete, working with state and federal agencies to construct new sewer pump station and parking lot on site.