Town of Putnam Valley Projects Update June 2026

Town of Putnam Valley Projects Overseen by J. Robert Folchetti & Associates (JRFA)  June 30, 2026

FEMA Projects

  • Wiccopee Road Culvert – Construction complete 
  • Bell Hollow Road Culvert – Construction complete 
  • Town Hall Parking Lot Retaining Wall – Construction complete
  • Town Park Beaches at Lake Peekskill and Oscawana Lake – Construction Complete
  • Brook Falls Road Culvert – Construction ongoing, to run through July 2026 – Bridge installed. Paving and site restoration completed. Project work to be completed fence and guiderail installation.
  • New Hill Road Culvert – 98% Design Complete working on NYSDEC and ACOE approvals, received New York State Office of General Services “no permit required” document. Temporary bridge installation during construction included in the design documents.

Capital Projects

  • Horton Hollow Road Bridge – 33% Design Complete working on engineering report, property acquisition documents and NYSDEC and ACOE approvals. 
  • Cimarron Road Culvert – Cimarron Road closed on May 18, 2026. Bridge installed and currently being backfilled. Work to be completed include paving, stormwater piping, site restoration and guiderail installation. 
  • Oregon Corners Substation Demolition – Demolition Complete, working with state and federal agencies to construct new sewer pump station and parking lot on site.