Town of Putnam Valley Projects Update August 2026

Town of Putnam Valley Projects Overseen by J. Robert Folchetti & Associates (JRFA)

 August 31, 2026

 

FEMA Projects

  • Wiccopee Road Culvert – Construction complete 
  • Bell Hollow Road Culvert – Construction complete 
  • Town Hall Parking Lot Retaining Wall – Construction complete
  • Town Park Beaches at Lake Peekskill and Oscawana Lake – Construction Complete
  • Brook Falls Road Culvert – Construction ongoing, to run through September 2026 – Bridge installed. Paving and site restoration completed. Bridge open to the public. Project work to be completed fence and guiderail installation estimated to be complete by mid-September.
  • New Hill Road Culvert – 100% Design Complete -Received NYSOGS “no permit required” document and NYSDEC Permit. Temporary bridge installation during construction is part of the design. Project is out to bid with bids due on September 23, 2026.

Capital Projects

  • Horton Hollow Road Bridge – 40% Design Complete working on engineering report, property acquisition documents and NYSDEC and ACOE approvals. 
  • Cimarron Road Culvert – Construction complete
  • Oregon Corners Substation Demolition – Demolition Complete, working with state and federal agencies to construct new sewer pump station and parking lot on site.