FEMA

  • Wiccopee Road Culvert – Construction complete 
  • Bell Hollow Road Culvert – Construction complete 
  • Town Hall Parking Lot Retaining Wall – Construction complete
  • Town Park Beaches at Lake Peekskill and Oscawana Lake – Construction Complete
  • Brook Falls Road Culvert – Construction ongoing, to run through June 2026 – Temporary bridge in use, footings for arched concrete culvert to be delivered week of March 2, 2026. Arched concrete culvert sections to be delivered week of March 9, 2026. New arched structure to be installed by April 30 with paving, site restoration and guiderail installation thereafter.
  • New Hill Road Culvert – 85% Design Complete working on NYSDEC and ACOE approvals. Temporary bridge installation during construction included in the design documents.
  • Cimarron Road Culvert – Bids received on January 12, 2026. Bid review and recommendation complete, bid award estimated on February 18, 2026. Construction to start approximately 45 days later.
  • Horton Hollow Road Bridge – 24% Design Complete working on engineering report, property acquisition documents, subsurface soil borings, tree removal and NYSDEC and ACOE approvals. 
  • Oregon Corners Substation Demolition – Bids received in December 2025. Bid award is estimated on February 18, 2026. Demolition takes place within 45 days of contract signing.